EPM Central Project Server Tutorials
Home Deployment    MS Project PWA SharePoint Articles Administrators FAQs Consulting Guest Book Search Site Map
Atricles

Project Server 2003

Project Server 2007

Project Server 2010

 
 
 
Articles -> MS Project -> Earned Value Analysis
 Overview  | Example  | Step 1  | Step 2  | Step 3  | Step 4  | Step 5  |

Earned Value Analysis - Example (Hands On)

Step 2 : Save Baseline

Steps:
  • On Tools menu -> Tracking -> Save Baseline
  • Click Save Baseline and the click the baseline (Ensure Baseline is the term in the Save Baseline dropdown list and the Entire Project radio button is highlighted.)
  • Press OK to save your baseline
  • Save Project Plan



Please verify the baseline information on Project Statistics window. (On Project menu -> choose Project Information -> Click on Statistics )





Please proceed to Step 3