Reason 1: Inability to preview updates prior to accepting PWA time from team members
Project Server 2003:
In Project Server 2003, there is no capability to preview the PWA updates prior to saving the project plan.
Project Managers are experiencing difficulty on changed dates and work hours in project plans after accepting the PWA updates.
Project Server 2007:
Project Server 2007 provides PMs with a Preview option prior to accepting and saving updates to the project plan.