Articles -> MS Project Server 2003 Limitations -> Reasons to Migrate Project Server 2007
Overview  |  Reason 1 | Reason 2  | Reason 3  | Reason 4  | Reason 5  | Reason 6  |  Reason 7   |  Reason 8 |

Reason 9 | Reason 10  | Reason 11  | Reason 12  | Reason 13  | Reason 14  |  Reason 15    | 


Reason 9: Inability to reschedule work based on resource vacation time


Scenario: PM want to assign the task to Software Development team. So based on availability, team member can self-assign the task. (or) Team lead can re-assign the task to next available team member


Project Server 2003:

In Project Server 2003, planned vacation time per resource appears as scheduled work. System does not update the resource calendars and not capable to reschedule the project work dynamically based on resource non availability.


Project Server 2007:

Submitting non working time (Vacation time) through the timesheet creates the resource calendar exceptions, so project work can be rescheduled automatically.