Republished Plan on a completed task
Project Server FAQs -> MS Project FAQ 3

I have republished my plan with more work on a completed task. It is still not showing up under current tasks in timesheet?


MS Project Server 2003: In Project Professional, highlight the tasks or assigments that are not showing up as you would expect. Do a collaborate>Publish>Republish Assignments. On the dialog box check the "Overwrite Actuals" checkbox. This will force a refresh of the task and the assignments.

Please read for more details: Collaborate ->Republish Assignments with “overwrite actual work