I have a task that is set to start in the future but is not showing up in my Current Tasks. MS Project Server 2003: Logon to PWA as administrator; Click Admin link -> Customize Project Web Access You can see at the very bottom of the page there is a definition of how many days in the future can a task start date be to be included in the Current Task. This is partly what drives the tasks that are included in your current tasks. For example if that setting is set to 10 days. Any task that has a start date within 10 days of the current date will show up in Current Tasks. In total Current Tasks will include all uncompleted tasks that are set to start within that setting date. |