EPM Central Project Server Tutorials
Home Deployment    MS Project PWA SharePoint Articles Administrators FAQs Consulting Search Site Map
     MS Project

Manage Project

Project Server Account

New Project

Preferred Options

  Resources
Resource Types
Enterprise Resources
Copy Assignments

     Tasks
Enter Tasks
Recurring Tasks
Key Tasks
Assignments
Task Dependency
Docs and URLs
Critical Path
Format Views

     Task Types
Overview
Fixed Units
Fixed Duration
Fixed Work

Effort Driven
Non Effort Driven

 Network Diagram

     Baseline
Overview
Save Baseline
View Baseline

 Collaboration

    Update Project
Overview
Enter Actuals
PWA Updates
Actual Work Protected

     Earned Value
Overview
Prerequisites
EV Terminology
Example

    Master Project
Overview
Create Master
Manage Links
Critical Path

   Export Gantt

  Help from Microsoft
Project 2003
Project 2007

     2007 Features

Local Cache

Open Project

Publish Project

Work Offline

Share Project

Program Plan

 
 
 
MS Project -> Baseline -> View Baseline
   After you’ve saved the baseline, you can view the baseline information by using one of the following methods.

  • Project Statistics dialog box
  • Apply Baseline table to Tracking Gantt
  • Add Baseline columns to Task table

Please remember, initially all the baseline columns are empty until you save a baseline.

Example:  Let’s say, You have a project called Project Office. You just created the project plan with all schedules and assignments. You didn’t save the baseline yet and no actuals are entered. Please use the Statistics dialog box to view the project information.

1) Project Statistics dialog box:

Steps
  • Open the project plan
  • On Project menu, choose Project Information
  • Click on Statistics
      

     Fig 1: Project information prior to save baseline ; no actuals reported

Please see in above fig, Baseline Start. Baseline Finish, Baseline Duration, Baseline Work and Baseline Costs are NA. This is due to; no baseline information is available for this project plan.


Also note that Actual Start, Actual Finish, Actual Duration, Actual Work and Actual Costs field are 0. This is due to: no actuals reported for this project.

Now, you save the baseline for this project. Please use Tools -> Tracking -> Save Baseline; Please choose Entire Project option. After you’ve save the baseline, please see again the project statistics information. (Fig. 2) Please note that baseline information should identical to the current information.


      

     Fig 2: Project information after saving the baseline, no actuals reported

After saving the baseline, you are ready track the project. Depends on the method you adopted (% Complete or Actual work reported by team member through PWA), you have to update the project. Once your project updated with progress, you can review the project’s current status by comparing with baseline.

Open the Project information dialog box again and view the baseline and actual info. (Fig 3)


      


In above fig, project has been accrued actual hours 40; also see the duration, now project is ending on 2/13 instead of 2/12. You see the one day variance on schedule.

2) Apply Baseline table to Tracking Gantt

Steps
  • Open the project plan
  • On View menu -> Choose Tracking Gantt
  • View -> Tables -> More Tables -> Baseline -> Apply


      


3) Add Baseline columns to Task table

On any Task view (Gantt Chart, Tracking Gantt), right click on any column to view and select the columns like "Baseline Cost, Baseline Duration, Baseline Finish, Baseline Start, Baseline Work Baseline1 Cost, Baseline1 Duration, Baseline1Finish etc."