EPM Central Project Server Tutorials
Home Deployment    MS Project PWA SharePoint Articles Administrators FAQs Consulting Search Site Map
     MS Project

Manage Project

Project Server Account

New Project

Preferred Options

  Resources
Resource Types
Enterprise Resources
Copy Assignments

     Tasks
Enter Tasks
Recurring Tasks
Key Tasks
Assignments
Task Dependency
Docs and URLs
Critical Path
Format Views

     Task Types
Overview
Fixed Units
Fixed Duration
Fixed Work

Effort Driven
Non Effort Driven

 Network Diagram

     Baseline
Overview
Save Baseline
View Baseline

 Collaboration

    Update Project
Overview
Enter Actuals
PWA Updates
Actual Work Protected

     Earned Value
Overview
Prerequisites
EV Terminology
Example

    Master Project
Overview
Create Master
Manage Links
Critical Path

   Export Gantt

  Help from Microsoft
Project 2003
Project 2007

     2007 Features

Local Cache

Open Project

Publish Project

Work Offline

Share Project

Program Plan

 
 
 
MS Project -> Earned Value -> Overview
   Earned Value Overview :

Earned value analysis is a procedure of measuring the cost of work performed up to the status date or current date.

Project schedule and cost measurements should be managed as integrated elements and not as separate items. If the project is over budgeted than planned or project’s tasks are getting delayed, you can know you may be in trouble. Earned Value analysis solves this issue by providing the information of schedule and costs variances related to a baseline plan. Earned value uses the original estimates saved with a baseline and progress of the plan reported on the project to determine whether project is on track in terms of duration and cost.

Earned value is always specific to a status date. Status date may be current date, a date in the past, or a date in the future. Setting the status date to the date you last updated project progress is always the best practice.

Earned Value compares the following information:
  • Planned Value: How much work you planned to have completed by now (usually calculated in dollars or hours)
  • Actual Cost: How much you have actually spent by now (usually calculated in dollars or hours)
Copyright © 2013. EPM Central. All rights reserved.