EPM Central Project Server Tutorials
Home Deployment    MS Project PWA SharePoint Articles Administrators FAQs Consulting Search Site Map
     MS Project

Manage Project

Project Server Account

New Project

Preferred Options

  Resources
Resource Types
Enterprise Resources
Copy Assignments

     Tasks
Enter Tasks
Recurring Tasks
Key Tasks
Assignments
Task Dependency
Docs and URLs
Critical Path
Format Views

     Task Types
Overview
Fixed Units
Fixed Duration
Fixed Work

Effort Driven
Non Effort Driven

 Network Diagram

     Baseline
Overview
Save Baseline
View Baseline

 Collaboration

    Update Project
Overview
Enter Actuals
PWA Updates
Actual Work Protected

     Earned Value
Overview
Prerequisites
EV Terminology
Example

    Master Project
Overview
Create Master
Manage Links
Critical Path

   Export Gantt

  Help from Microsoft
Project 2003
Project 2007

     2007 Features

Local Cache

Open Project

Publish Project

Work Offline

Share Project

Program Plan

 
 
 
MS Project -> Earned Value -> Prerequisites
   Earned Value Prerequisites :

   To calculate the Earned Value, all the following activities must be performed in your project plan.
  • Resources assigned to tasks
  • Resources should have Rate information
  • Summary tasks should not have resources assigned
  • Saved Baseline
  • Updated project progress

  Earned Value Calculations:

Earned value calculations are based on following factors. To get the accurate EV numbers, you need to specify the below three settings on MS Project Plan.
  • Status Date
  • Baseline number
  • EV Calculation Method
Status Date:  Status date may be current date, a date in the past, or a date in the future. Setting the status date to the date you last updated project progress is always the best practice.

Steps:
    1)Under Project menu, choose Project Information
    2)Select Status Date and click OK
    3)Save Project Plan

   


Baseline Number: If you have multiple baselines saved for your project, you have a option to specify which baseline that you want to consider for EV Calculations.


EV Calculation Method: Earned value calculations always based on % Complete or Physical % Complete

% Complete vs. Physical % Complete:  Percent Complete is a calculation field and MS project calculates the value based on actual work and duration that you entered. Also if you enter directly the Percent Complete value, MS Project calculates the Actual and Remaining Duration for the task.

Physical Percent Complete is always entered directly by you. MS Project will not calculate the value for this column. Use physical percent complete when Percent Complete would not be an accurate measure of actual work and cost information.

Steps:
    1)Under Tools menu, choose Options
    2)Click on Calculation tab and Click on Earned Value
    3)Choose Default task Earned Value method and Baseline for Earned Value calculations from dropdown and click OK
    3)Save Project Plan



   


Copyright © 2013. EPM Central. All rights reserved.