EPM Central Project Server Tutorials
Home Deployment    MS Project PWA SharePoint Articles Administrators FAQs Consulting Search Site Map
     MS Project

Manage Project

Project Server Account

New Project

Preferred Options

  Resources
Resource Types
Enterprise Resources
Copy Assignments

     Tasks
Enter Tasks
Recurring Tasks
Key Tasks
Assignments
Task Dependency
Docs and URLs
Critical Path
Format Views

     Task Types
Overview
Fixed Units
Fixed Duration
Fixed Work

Effort Driven
Non Effort Driven

 Network Diagram

     Baseline
Overview
Save Baseline
View Baseline

 Collaboration

    Update Project
Overview
Enter Actuals
PWA Updates
Actual Work Protected

     Earned Value
Overview
Prerequisites
EV Terminology
Example

    Master Project
Overview
Create Master
Manage Links
Critical Path

   Export Gantt

  Help from Microsoft
Project 2003
Project 2007

     2007 Features

Local Cache

Open Project

Publish Project

Work Offline

Share Project

Program Plan

 
 
 
MS Project -> Earned Value -> EV Terminology

Please note that all the following Earned Value terms will be expressed in terms of cost terms.
  • BAC (Budgeted at Completion): An estimate of the total project baseline cost.
  • BCWP (Budgeted cost of work performed): How much did we budget for the work we’ve done? BCWP is the cost of the task work actually done. BCWP calculation uses the % work complete value. BCWP is also called as Earned Value.
  • BCWS (Budgeted Cost of Work Scheduled): How much work should be done by now?
    BCWS value is original estimated of budgeted cost till Status Date. It uses the % complete value.
  • ACWP (Actual cost of work performed): This field shows the actual cost incurred on a task. (How much did we actually spend till Status Date). This is a cumulative sum of the actual cost incurred on a task as of status date.
  • CV (Cost Variance): The difference between the budgeted cost (BCWP) and actual cost (ACWP)is called as Cost Variance.

    CV = BCWP - ACWP

    If the CV is negative value, it implies that the task is currently over budget. If the CV is positive value, it implies that the task is currently under the budgeted amount.
  • SV (Schedule Variance): The difference between the BCWP and BCWS is called SV.

    SV = BCWP - BCWS

    If the SV is negative value, it implies that the project is currently behind schedule. If the SV is positive value, it implies that the project is currently ahead of the schedule in terms of cost.
  • CPI (Cost Performance Index): Ratio of budgeted cost of work performed to actual costs of work performed.

    CPI = BCWP/ACWP

    CPI < 1 indicates an over budget condition
  • SPI (Schedule Performance Index): The ratio of the budgeted cost of work performed to the budgeted cost of work scheduled.

    SPI = BCWP/BCWS

    SPI < 1 indicates a behind schedule condition


Copyright © 2013. EPM Central. All rights reserved.