EPM Central Project Server Tutorials
Home Deployment    MS Project PWA SharePoint Articles Administrators FAQs Consulting Search Site Map
     MS Project

Manage Project

Project Server Account

New Project

Preferred Options

  Resources
Resource Types
Enterprise Resources
Copy Assignments

     Tasks
Enter Tasks
Recurring Tasks
Key Tasks
Assignments
Task Dependency
Docs and URLs
Critical Path
Format Views

     Task Types
Overview
Fixed Units
Fixed Duration
Fixed Work

Effort Driven
Non Effort Driven

 Network Diagram

     Baseline
Overview
Save Baseline
View Baseline

 Collaboration

    Update Project
Overview
Enter Actuals
PWA Updates
Actual Work Protected

     Earned Value
Overview
Prerequisites
EV Terminology
Example

    Master Project
Overview
Create Master
Manage Links
Critical Path

   Export Gantt

  Help from Microsoft
Project 2003
Project 2007

     2007 Features

Local Cache

Open Project

Publish Project

Work Offline

Share Project

Program Plan

 
 
 
MS Project -> Master Project -> View Critical Path

By default, MS Project treats inserted projects as summary tasks, so, MS project calculates a single critical path across all projects by using the latest finish date of the project. Due to this nature, a subproject within master appears like they don’t have critical paths of their own.

To see the critical path for each subproject, you have to specify the following settings:
  • On master project, Tools menu -> Options -> Calculation tab -> uncheck the option “Inserted projects are calculated like summary tasks”
With above setting, MS project calculated for the mater project independent of subprojects, and also calculates the critical path for each subproject.

Copyright © 2013. EPM Central. All rights reserved.