EPM Central Project Server Tutorials
Home Deployment    MS Project PWA SharePoint Articles Administrators FAQs Consulting Search Site Map
     MS Project

Manage Project

Project Server Account

New Project

Preferred Options

  Resources
Resource Types
Enterprise Resources
Copy Assignments

     Tasks
Enter Tasks
Recurring Tasks
Key Tasks
Assignments
Task Dependency
Docs and URLs
Critical Path
Format Views

     Task Types
Overview
Fixed Units
Fixed Duration
Fixed Work

Effort Driven
Non Effort Driven

 Network Diagram

     Baseline
Overview
Save Baseline
View Baseline

 Collaboration

    Update Project
Overview
Enter Actuals
PWA Updates
Actual Work Protected

     Earned Value
Overview
Prerequisites
EV Terminology
Example

    Master Project
Overview
Create Master
Manage Links
Critical Path

   Export Gantt

  Help from Microsoft
Project 2003
Project 2007

     2007 Features

Local Cache

Open Project

Publish Project

Work Offline

Share Project

Program Plan

 
 
 
MS Project -> Preferred Options
   1) Set the date format for Tasks

    Tools menu -> Options -> Click on View tab -> Choose the Date format from dropdown -> Click OK

   2) Specify default view for your project plan

    Tools menu -> Options -> Click on View tab -> Under Default view, choose the required view from dropdown -> Click OK

    Next time, when you launch the Project, specified default view will be loaded.

   3) Save and Publish assignments on every update of Project Plan

     Tools -> Options -> Collaborate -> Under "On every save, publish the following information to Project Server" -> New and Changed Assignments/Project Summary/Including full project plan

   4) Change Time Scale on Task Usage/Resource Usage View

     Three tier view (top, middle and bottom):

    This option is best suitable to show the three tier time scale, Years at top; Months at Middle;
Weeks at bottom

Steps:
  • Format menu -> Time Scale -> Click on Top Tier tab -> Under “Time Scale Options -> Choose “Three Tiers (Top, middle, bottom)
  • Under “Top Tier Formatting” -> Under “Units” -> Choose “Years” and also choose “Label” for format
  • Click on Middle Tier tab -> Under “Middle Tier Formatting” -> Under “Units” -> Choose “Months” and also choose “Label” for format
  • Under “Bottom Tier Formatting” -> Under “Units” -> Choose “Weeks” and also choose “Label” for format
  • Click OK to apply the changes


   5) Specify Earned Value Calculations

  • Under Tools menu -> Options
  • Click on Calculation tab and Click on Earned Value
  • Choose Default task Earned Value method and Baseline for Earned Value calculations from dropdown and click OK