EPM Central Project Server Tutorials
Home Deployment    MS Project PWA SharePoint Articles Administrators FAQs Consulting Guest Book Search Site Map
     MS Project

Manage Project

Project Server Account

New Project

Preferred Options

  Resources
Resource Types
Enterprise Resources
Copy Assignments

     Tasks
Enter Tasks
Recurring Tasks
Key Tasks
Assignments
Task Dependency
Docs and URLs
Critical Path
Format Views

     Task Types
Overview
Fixed Units
Fixed Duration
Fixed Work

Effort Driven
Non Effort Driven

 Network Diagram

     Baseline
Overview
Save Baseline
View Baseline

 Collaboration

    Update Project
Overview
Enter Actuals
PWA Updates
Actual Work Protected

     Earned Value
Overview
Prerequisites
EV Terminology
Example

    Master Project
Overview
Create Master
Manage Links
Critical Path

   Export Gantt

  Help from Microsoft
Project 2003
Project 2007

     2007 Features

Local Cache

Open Project

Publish Project

Work Offline

Share Project

Program Plan

 
 
MS Project 2007 -> MS Project Server 2007 - Work Offline
  
Project Server 2007 introduces a new client-side cache and caching service. By having local cache mechanism, Project Server 2007 and Project Professional 2007 allows us to work offline on project plans.

Work Offline feature is more convenient and handy feature when you away from company network and internet connection. You can able to work on project plan when you travelling by air.



Step 1: Prepare project in Offline mode:
  • Launch Project Professional 2007 by connecting to Project Server
  • Open the enterprise project you want to work offline
  • Click on File menu -> Close to close the project
  • You will see the following prompt you to get the confirmation from you regarding whether you want to checkin project



  • In the confirmation window, click on “No” to close the project but leave it in a checked-out state. (It’s an important to keep the project in checked-out state, so no other user opens the same project and perform any edits while you are working with in offline)
  • Click on File menu -> Exit to the exit Project Professional 2007
By doing the above step, the latest version of project from server loads into your Local cache.



Step 2: Perform Edits in Offline mode:
  • Launch Project Professional 2007
  • In the Login dialog box, select the your Project Server login account from Profile dropdown (Please do not select Computer account from dropdown)
  • Click on Work Offline button



  • Project Professional 2007 launches in Offline mode (Verify the status bar at below, it should display “Offline” )
  • Click on File menu -> Open
  • You will see the list of the projects saved in the Local Cache, select your offline project and click the Open. (Notice that Cache Status column will have “Checked Out” for this project. If you are not seeing the Cache Status in Open dialog click the list icon in the upper right corner of the dialog box)
  • Edit the project as needed
  • Once you done with edits, click on File menu -> Save to the save the Offline project in the Local Cache
  • Click on File -> Close to close the Offline project
  • Click No to the prompt on regarding Checkin Project
  • Click on File menu -> Exit to exit the Project Professional 2007



Step 3: Save Offline Changes to the Sever:

Once you return to company network and internet connection, you have to apply offline edits to server.
  • Launch Project Professional 2007 by connecting to Project Server
  • Click on File menu -> Open
  • Select offline project and click on Open button
  • Click on File menu -> Save to apply your offline edits to project in the server
  • Click on File menu -> Close the project plan
  • Click on “Yes” to check in the project on prompt to get the confirmation from you regarding whether you want to checkin project





Related Topic:

Share Project Plan with External Users