EPM Central Project Server Tutorials
Home Deployment    MS Project PWA SharePoint Articles Administrators FAQs Consulting Search Site Map
     MS Project

Manage Project

Project Server Account

New Project

Preferred Options

  Resources
Resource Types
Enterprise Resources
Copy Assignments

     Tasks
Enter Tasks
Recurring Tasks
Key Tasks
Assignments
Task Dependency
Docs and URLs
Critical Path
Format Views

     Task Types
Overview
Fixed Units
Fixed Duration
Fixed Work

Effort Driven
Non Effort Driven

 Network Diagram

     Baseline
Overview
Save Baseline
View Baseline

 Collaboration

    Update Project
Overview
Enter Actuals
PWA Updates
Actual Work Protected

     Earned Value
Overview
Prerequisites
EV Terminology
Example

    Master Project
Overview
Create Master
Manage Links
Critical Path

   Export Gantt

  Help from Microsoft
Project 2003
Project 2007

     2007 Features

Local Cache

Open Project

Publish Project

Work Offline

Share Project

Program Plan

 
 
MS Project -> Tasks -> Assignments
    
Resource Assignments:

When you assign a resource to a task, MS Project schedules the resource’s work to start at the time that task is scheduled to start. Generally, project only schedules work during the dates and times that are defined as working time on the resource’s calendar. Task schedule totally depends on resource working time on resource calendar.

Once you added resources to project plan, resources can assign to the tasks. You can use Gantt chart or Task form to assign the resources to tasks.

You can assign the resources to task by one of the following methods:

a) Gantt chart: On Gantt chart, use the Resource name column to assign the resource. If you click on cell under Resource Name, you will see all the resource names which are already added in to the project.



b) Task Information dialogue box: On Gantt chart view, double click on task name to view the task information. Choose the Resource tab



c)Task form: On Gantt chart, click on Window menu and choose Split to display the Task form in the bottom pane. Click on required task name from top pane to enter the resource names. You have to enter the resource names from bottom pane under Resource Name.



Please always note the resource units for each resource, which plays important role in scheduled work for each resource.

If a resource unit is assigned 100% to a task, Project schedules 100% of the hours in the calendar for that resource. However, if the resource unit is assigned to a task at 505, Project only schedules 50% of the available hours on any given day.

MS Project calculated the work as follows:

Work = Duration * Unites

i.e. Duration = Work/Unites