EPM Central Project Server Tutorials
Home Deployment    MS Project PWA SharePoint Articles Administrators FAQs Consulting Search Site Map
     MS Project

Manage Project

Project Server Account

New Project

Preferred Options

  Resources
Resource Types
Enterprise Resources
Copy Assignments

     Tasks
Enter Tasks
Recurring Tasks
Key Tasks
Assignments
Task Dependency
Docs and URLs
Critical Path
Format Views

     Task Types
Overview
Fixed Units
Fixed Duration
Fixed Work

Effort Driven
Non Effort Driven

 Network Diagram

     Baseline
Overview
Save Baseline
View Baseline

 Collaboration

    Update Project
Overview
Enter Actuals
PWA Updates
Actual Work Protected

     Earned Value
Overview
Prerequisites
EV Terminology
Example

    Master Project
Overview
Create Master
Manage Links
Critical Path

   Export Gantt

  Help from Microsoft
Project 2003
Project 2007

     2007 Features

Local Cache

Open Project

Publish Project

Work Offline

Share Project

Program Plan

 
 
MS Project -> Enter Tasks
    

Tasks: You can create a task by typing a name in the “Task Name” field in one of the rows of the task sheet portion of the Gantt chart.

Enter Task Details:

Steps:
  • Open the project plan (or blank project)
  • View menu -> Gantt chart
  • Select a cell in the Task Name column
  • Type the task name; complete the cell entry by pressing Enter

After completing the cell entry, project fills in default duration of 1 day for the new task, and defaults start and finish dates for the task. Then your cursor stays at new row for you to enter the next task.

Please set the required duration for task. Generally MS Project will calculate the schedule dates based on duration, resource units and task dependencies.

Inserting a task between other tasks:

Steps: Select a cell in the row where you want the new task to appear Insert menu ->New Task

Delete task:

Select a cell of the task that you want to delete
Edit menu -> Delete Task

Intending Tasks (Grouping tasks in to Phases)

Tasks in project plan need to be organized into group of activities that represents major phases of a project. This is equivalent of the Work Breakdown Structure (WBS). The major phase is a summary task and you do not have ability to modify the details of summary task. Summary task start date is the earliest start date of any of its subtasks, and finish date is the latest finish date of any of its subtasks.

Example:

Suppose I have the following tasks in Gantt chart:
  • Client meetings
  • Draw data flow diagrams
  • Prepare functional diagram
  • Lists current system limitations

I would like to define all the above tasks under task (phase) called “Requirements Specifications”

Steps:
  • List tasks on Gantt chart under Task Name column

  • Insert a new task called “Requirements Specifications” as a first task





  • Select all the detailed tasks and choose “->” On tool bar





  • Now, Gantt chart displays the summary and detailed tasks as follows:





Copyright © 2013. EPM Central. All rights reserved.