EPM Central Project Server Tutorials
Home Deployment    MS Project PWA SharePoint Articles Administrators FAQs Consulting Search Site Map
     MS Project

Manage Project

Project Server Account

New Project

Preferred Options

  Resources
Resource Types
Enterprise Resources
Copy Assignments

     Tasks
Enter Tasks
Recurring Tasks
Key Tasks
Assignments
Task Dependency
Docs and URLs
Critical Path
Format Views

     Task Types
Overview
Fixed Units
Fixed Duration
Fixed Work

Effort Driven
Non Effort Driven

 Network Diagram

     Baseline
Overview
Save Baseline
View Baseline

 Collaboration

    Update Project
Overview
Enter Actuals
PWA Updates
Actual Work Protected

     Earned Value
Overview
Prerequisites
EV Terminology
Example

    Master Project
Overview
Create Master
Manage Links
Critical Path

   Export Gantt

  Help from Microsoft
Project 2003
Project 2007

     2007 Features

Local Cache

Open Project

Publish Project

Work Offline

Share Project

Program Plan

 
 
 
MS Project -> Update Project
   Update Project:


Various options are available to update MS Project plan. Based on your preference and method of progress, you can use the Gantt chart, Tracking Gantt and Task Usage views.

The following tracking fields are calculated by MS Project when information is entered in one of the others in following list:

Actual work; Actual cost; Actual Start Date; Actual Finish Date: Percent of Work Complete; Percent Complete; Remaining Work

Prior to enter the actual info, you need to do the following:
  • Set the Status Date
  • Calculation settings
  • Select the tracking view (Gantt chart or Task usage view)


1) Status Date:  Before you updating the project plan, set the status date field. MS Project uses the status date for calculations to determine remaining work/duration/variance etc.

If you don’t set the status date, MS Project uses the current date to recalculate the schedules and work.

Set Status Date:
  • On Project menu -> Project Information -> select the date you want to use for actuals

2) Calculation Settings: Project contains several calculation options that affect the project schedule and costs.

Steps: Tool menu -> Options -> Calculations tab






3) Tracking View

You can use Gantt chart to record tracking information. The best way is, apply the Tracking table to Gantt chart, so you can record % complete; actual work; actual start etc.

You can use the any of the following method to record Actuals:
  • Percent Complete
  • Actual durations
  • Work Completed
  • Actual Work

Note: If you are using the MS Project Server with time sheet functionality, please don’t enter actuals directly on project plan. It’s always good practice to get the actuals from team member through PWA.



Copyright © 2013. EPM Central. All rights reserved.