The Project Center within PWA provides the web portal view about project information and status about projects.

From the Project Center view, you can do the following:

  • View Project Summary
  • Project Schedule (Gantt chart view)
  • Add enterprise resources into project plan
  • Open project plan
  • Open Master Project
  • View SharePoint site

Project Summary  |Project Schedule  |Add Resources |Open Project  |Master Project  |Project Workspace

Add enterprise resources into project plan

Steps:

Enterprise resources can be added to project through Project Center in PWA as well as Project Professional.

Note: You should have “Build Team” permissions to do this operation. Please contact your Project Server administrator on any access questions.

Steps:

  • On PWA -> Click on link “Projects” from top menu
  • Highlight the appropriate project and click the “Build Team icon”



  • The Build Team page will be displayed. Please click "View All" to list all the enterprise resources. Optionally you can define the filter to select the resources.



  • Click on "Save Changes" to add the resource names