PWA 2007 -> Change Ownership

You can change the ownership of the project by editing project information for selected project in Project Center.

Steps:
  • Click on “Project Center” link on PWA home page



  • Project list will be displayed
  • Highlight the project that you want to change the ownership; Click on Edit Project Properties



  • Choose the new project manager name from dropdown
  • Click on Save and Publish



  • You will see the Save and Publish status message in upper left corner, when finished, Click on Close button
  • Click on Cancel to go back to Project Center